If the AI bubble pops, the people most likely to be left with the bill are the lenders and the towns that agreed to host the buildings. The data centers, power plants and fiber don't disappear when a stock falls. This letter follows the debt, explained for anyone outside finance.
Big Tech is borrowing to build. Microsoft, one of the richest companies on earth, borrowed 25 billion dollars in late October, its first US bond sale since 2017. Each borrower pays a different price, from the safest giants to the riskier new cloud companies. And who holds that debt? Life insurers, bond funds and pension plans are some of the biggest holders of corporate bonds, so if you have a pension or a bond fund, you may already be one of the lenders.
Planned is not built. In June the Texas grid operator was tracking requests for 438 gigawatts of new demand, with only about 6 gigawatts switched on. Permission is getting expensive too: in a Quinnipiac poll, 71 percent of Americans said they would oppose an AI data center in their community.
We have seen this before. In the 2000 telecom bust, Lucent lent its customer Winstar 2 billion dollars, and Winstar went bankrupt. The fiber left behind still sells today. A power plant is different, because someone has to keep paying for it.
That is why Wisconsin made data center builders with weaker credit post collateral before the utility builds power plants for them. My take: a balance sheet doesn't clear a town vote, and the rules that protect the neighbours decide who pays. Not financial advice.
Not financial advice. Apple, Microsoft, Meta, Oracle, CoreWeave, Nvidia, Amazon, Verizon and Duos are publicly traded companies.
Chapters
- 0:00 Is AI a bubble, and who pays if it pops?
- 0:36 Do the data centers disappear if AI crashes?
- 0:54 Why did the Nasdaq have its worst day since April 2025?
- 1:36 Why did Microsoft borrow $25 billion?
- 2:46 Who is lending money to AI? Maybe you
- 3:00 Why do towns say no to data centers?
- 3:33 What happened in the 2000 telecom bust?
- 4:36 What happens to a power plant built for a data center?
- 5:12 Can a data center sell its power to the town?
- 5:31 Who pays if a data center fails? Wisconsin's answer
- 6:18 What does a safe data center deal look like?
- 7:06 Operator's Corner
- 7:40 My take
Full transcript
Everyone's asking the same question right now. Is AI a bubble? I want to ask a better one. If it pops, who's left holding the stuff it built?
Because a bubble isn't only stock prices. It's buildings. Power plants. Glass in the ground. And a lot of borrowed money. Today we follow the debt, all the way down to the town that said yes.
This is The Last Mile Letter. I'm Tobe. I've spent my career building the networks the internet runs on, and every week I explain the stuff behind your screen in plain English.
Myth or fact: if the AI bubble pops, the data centers disappear.
Myth. A stock price can vanish in an afternoon. A building can't. Neither can the power plant next to it, or the fiber running into it.
So the real question is who owns all of it when the money stops.
On Thursday, November 5th, the Nasdaq fell about five and a half percent. Its worst day since April 2025.
Part of the reason: in the midterms, data centers turned into a power bill issue. By one count, governors or governors-elect in nine states now back a pause on new data centers. Those states hold about 41 percent of all the data center capacity planned in the U.S.
A pause isn't a cancellation. And planned isn't built. In June, the Texas grid operator was tracking requests for 438 gigawatts of new demand, mostly data centers. Only about 6 had switched on.
A lot of this is still a press release with a number on it.
So who gets through this? Follow the debt. Microsoft is one of the richest companies on earth. In late October it borrowed 25 billion dollars anyway. Its first bond sale in the U.S. since 2017.
Why borrow when you have the cash? Same reason a family with savings still takes a mortgage. Cheap, long money for something that lasts. Here's how I read the move. Compute is turning into a utility. Financed like a power plant. Priced like one too.
But lenders don't charge everyone the same.
Apple borrowed about seven and a half billion dollars this month. It paid roughly five percent. And that money isn't even for AI. Meta borrowed 15 billion. It paid around six percent. Oracle pays about six and a half percent on its long-term debt. Its credit rating sits one notch above junk. And CoreWeave, one of the new AI cloud companies? In October, some of its bonds yielded around 15 percent.
Same market. Very different prices. The giants can still get money. For the newer players it's harder, and a lot more expensive. My take: this build was never short of money. It's short of borrowers that lenders trust.
So who's lending all this money? Quite possibly you. Life insurers, bond funds and pension plans are some of the biggest holders of corporate bonds in the U.S.
If you have a pension or a bond fund, you may already be one of the lenders.
And this is where it gets weird. A strong balance sheet doesn't clear a town vote.
In one national poll this fall, 71 percent of Americans said they'd oppose an AI data center in their own community.
In October, Amazon pledged a billion dollars to the towns that host its data centers. That's not generosity. That's the price of permission.
Power was the last gate. Permission is the new one. Ground that already has power, in a town that already said yes, is now the scarcest thing in the whole build.
So say the music stops. What's left? We've seen this movie. Around 2000, telecom companies borrowed huge sums to lay fiber everywhere. And the companies selling the gear were lending their own customers the money to buy it. Lucent lent one customer, Winstar, 2 billion dollars. Winstar went bankrupt.
Sound familiar? This August, Nvidia lined up more than 500 billion dollars from six big investment firms, to help its customers afford its chips. That's investors' money, not Nvidia's own. But it rhymes. Back then, demand came slower than the plan. In Seattle, the local paper estimated about 95 percent of the new fiber under city streets sat dark. Unused.
Investors lost a fortune. But the glass stayed in the ground. Other companies bought it cheap and lit it up. And it still sells. This summer, Verizon signed a deal worth over a billion dollars for Google to use its dark fiber. What survived the last bust wasn't the gear. It was the ground underneath it.
But here's my worry. A power plant isn't fiber.
Glass in the ground can be switched on later by somebody else. A gas plant built for one data center is a different animal. Earlier this year, one analysis counted about 56 gigawatts of planned data centers bringing their own power. Mostly natural gas.
The chips inside get replaced every few years. A gas plant is built to run for decades. So here's the question nobody is pricing yet. When the data center a plant was built for goes bust, does that power find its way back to the grid? Or does it strand with it?
So why not just sell that power to the neighbours? In general, a plant like that can't sell straight to your house. It has to go through the grid operator and the state.
And those rules are being written right now. The federal energy regulator told all six big U.S. grid operators to fix theirs. Answers are due in mid-November.
So who pays if it goes wrong? The lenders take the first hit. The town is next. Its promised jobs and taxes need a tenant. And your bill? That depends on where you live, and who wrote the rules. Wisconsin wrote one. If a data center company's credit rating is below a set bar, it has to post collateral before the utility builds power plants for it. For Oracle, that meant more than 100 million dollars a year. It sued, then dropped the suit in August.
Wisconsin didn't block the data center. It repriced who's allowed to build one. If the builder walks away, the neighbours aren't left paying for the plant. In Canada, Ontario's draft plan says data centres should pay the full cost of their power and their grid upgrades.
Same technology. Different rules, different bill.
To be fair, this isn't all a bubble waiting to pop. A lot of the demand is real, especially for running AI after it's trained. And one small company showed how to build without getting stuck. Duos Edge AI signed a ten-year deal with a publicly traded cloud company. It covers 20 megawatts. It's worth over 400 million dollars. The capacity doesn't come online until 2027.
Note the order. Tenant signed. Then concrete. And the next wave is going smaller. Lots of sites, from about a megawatt at the edge to ten or twenty megawatts for a region.
My read: that's where most of the next wave lands, while the rules get fought over. And the neighbours have fair points both ways. Jobs and taxes. Bills, water and noise.
Quick one for my industry folks. A request for power is worth nothing. A signed, creditworthy tenant on ground that already has power is worth a lot. Lenders aren't pricing the chips. They're pricing the customer behind them. Borrowing to build, and renting out the megawatt, is a real Step 1. It funds everything. The trap is stopping there, as a levered landlord of a commoditizing asset with no signed customer. That's who gets stuck when the cycle turns. Contract first. Then own the outcome that runs on the megawatt, not just the lease.
Here's my take. We need rules. Not rules that stop the build. Rules that make sure the people living next door get a fair deal on their bill. Skip the guardrails and we repeat what we did before. Rail lines to nowhere. Fiber that sat dark for years. Stranded assets. Build it right, and even if the bubble pops, the town keeps something useful.
Here's your line for dinner tonight: everyone's asking if AI is a bubble. Better question: if it pops, who's holding the stuff it built?
P.S. In the networks I've run, the cheapest new capacity was rarely a new build. It was the fiber already in the ground. New gear on each end, no new permits, no digging up a street. When money gets tight, that's what holds its value. The stuff that's already plugged in. That's the letter. I'll see you at the last mile.
Sources
- Kotak Neo: US stock market falls as Nasdaq and Dow slide on tech selloff (2026-11-06)
- Bloomberg via Insurance Journal: tech selloff and data center pause pledges (2026-11-06)
- AI Weekly: Cleanview, 158.6 GW of US data center plans face governor pauses (2026-11-06)
- explainx: Midterms and the data center pipeline at risk, claimed vs verified (2026-11-05)
- The Next Web: Microsoft's $25 billion bond sale, its first since 2017 (2026-10-29)
- Bloomberg via Business Standard: Microsoft's $25 billion blowout bond puts it in AI winners' circle (2026-10-30)
- 24/7 Wall St.: Apple is borrowing $7.5 billion, its first bond sale since 2025 (2026-11-06)
- 9to5Mac: Apple bond sale, citing Bloomberg
- Reuters via The Star: Meta raises $15 billion in five-part US bond sale to fund AI expansion (2026-11-04)
- Newsquawk: Investors placed as much as USD 58bln of orders on Meta's bond offering (2026-11-03)
- Newsquawk: Meta launches USD 15bln five-part bond
- Computing: Oracle under pressure after ratings downgrade over AI expansion (2026)
- MarketBeat: Oracle is one step from junk. Can it afford the AI boom?
- investingLive: CoreWeave bonds trade like distressed debt (2026-10-15)
- RuntimeWire: CoreWeave bond yields above 15% (2026-10-14)
- Finviz: CoreWeave bond yields reach 15% as investors reassess AI infrastructure financing risks (2026-10-19)
- Walnut: Corporate bond statistics, holders of US corporate bonds (updated Oct 2026)
- Global Macro Monitor: Major holders of the US corporate bond market (2018-06-12)
- Federal Reserve: Financial Accounts of the United States (Z.1)
- PBS NewsHour: Boom and bust, the telecommunications industry (2001-08-31)
- Seattle Times: Fiber-optic lines languish under scarred city streets (2002-01-13)
- Techfinitive: The infrastructure nobody wanted is the infrastructure everyone uses
- Fierce Network: Verizon touts $1B deal with Google to connect AI data centers (2026-07-27)
- Lightwave: Verizon takes on $1B dark fiber data center deal with Google
- National Association of Manufacturers: Behind-the-meter AI projects surge in US (2026-02-06)
- Live in the Future: The interconnection queue fossil backdoor
- Cleanview (Distilled): Bypassing the grid, how data centers power themselves
- McGuireWoods: FERC issues Section 206 show cause orders on large load integration rules (2026-06-22)
- MGRID: All six grid operators ask FERC for 90 more days on large load rules (2026-08-13)
- RMI: Understanding FERC's large load orders (2026-07-06)
- K&L Gates: commentary on FERC's PJM co-location order
- National Law Review: FERC show cause orders seek to accelerate large load interconnections
- McCarthy Tetrault: Ontario launches Data Centre Playbook (2026-08-13)
- Power Engineering: Can ERCOT's new Batch Zero process alleviate the burden of 438,000 MW of large load requests? (2026-06-29)
- Data Center Frontier: ERCOT puts Texas AI megawatts to the test (2026-08-31)
- GlobeNewswire via Finviz: Duos Technologies announces 20 MW customer agreement (2026-10-20)
- DatacenterDynamics: Duos secures cloud provider as customer for 20MW of data center capacity
- New York Times via GV Wire: Amazon promises more local funding and less secrecy around data centers (2026-10-02)
- ABC News: Amazon to invest $1B in data center communities amid backlash
- eWeek: Vendor Financing Backfires (2001-04-23)
- Tomasz Tunguz: Nvidia and Nortel, a vendor financing comparison
- Reuters via Semafor: Nvidia partners with lenders to finance AI infrastructure (2026-08-10)
- Bloomberg via Fortune: Nvidia's $500 billion AI financing (2026-08-11)
- Wisconsin Watch: Oracle drops lawsuit challenging Wisconsin data center credit rules (2026-08-17)
- WPR: Oracle drops Wisconsin suit over financial requirements for data centers (2026-08-17)
- Wisconsin Watch: Oracle sues Wisconsin regulators over data center credit requirements (2026-06-23)
- Latitude Media: Does Oracle actually have a case against Wisconsin's data center rule? (2026-07-01)
Background reading (read during research, not quoted in the video):
Hosted by my AI digital twin (HeyGen), from my own research and analysis. Not financial advice.
Watch the series: Start Here